BSCC NewsTimetable/Status as of March 2008The whole eight and one-third yards The Steam Team have put in another month’s effort and the chassis has been joined back together.
These pictures show all the chassis frames welded and bolted
into position, as well as the front four boiler boxes in position. Boilers Boilers No. 4,5 and 6 are in production. Rear Fins The striking, twin vertical, rear fins of the car are in construction. They have an aluminium core and carbon composite skins. The angle of attack can be adjusted to help in tuning the cars handling.
Support Rigs The power rigs will provide power to the car during start up. This is required to drive the burner fans, charge the batteries, and run the sensor and control equipment. The two rigs are in and advanced stage of assembly.
Fire Training The team have had a preliminary visit from a fire safety and training officer. A program of training and risk assessment is being put together so that the start up and turn around crews can be given appropriate training as the team learn how to operate the car. BBC Filming Provisional filming days have been booked in late May for the BBC’s James May to visit the project and hopefully drive the car. April Steam? During the next month we will populate the chassis with boilers,
intakes and control boxes begin the task of plumbing and wiring
all of the water, gas, air and electrical services. The April
update will keep you informed of progress. |
||||||||
|